Skip to content
Ashforte
Case Example — Illustrative

Defence against an employer-issued LD notice on a healthcare build

A buildings contractor received a LD notice of USD 8.5M on a hospital project completed six months late. Ashforte built the defence position, quantified concurrent-cause exposure and negotiated a settled resolution.

Sector
Buildings — Healthcare
Contract
Amended FIDIC Yellow
Scale
USD 165M contract value
Region
Middle East
Outcome
LD exposure reduced through negotiated settlement
Illustrative example — The following are illustrative case studies representing the type of engagements Ashforte is built to deliver. Client identities, project details and figures are anonymised composites drawn from patterns typical to contractor-side commercial and claims work.
Section 01

The situation

The project reached practical completion six months late. The Employer issued a formal LD notice claiming the maximum contractual amount — approximately USD 8.5M.

The contractor's position was that a substantial portion of the delay was attributable to Employer-caused events (late design releases, changed scope, delayed approvals) and that concurrent-cause principles applied to the balance.

Prior EOT submissions during the project had been rejected on procedural grounds and the contractor had not maintained a live claim position through delivery. Defence had to be built from the record base that existed — which was uneven.

Section 02

Ashforte's intervention

The engagement was structured around the following workstreams, delivered by a senior-led team operating to Ashforte's standardized delivery protocols.

Phase 01

Defence positioning

  • Contract position review — LD clause, cap analysis, mitigation of loss
  • Record base audit — what could be substantiated from existing records
  • Employer-cause identification across the project timeline
  • Concurrent-cause analysis with contract-form specific treatment
Phase 02

Rebuttal construction

  • Point-by-point response to the LD notice
  • Employer-cause quantification with cause-and-effect narrative
  • Concurrent-delay treatment documented explicitly
  • Mitigation-of-loss argument based on Employer's operational commencement date
Phase 03

Negotiation

  • Formal rebuttal submission
  • Without-prejudice discussions across four sessions
  • Package settlement framework including release of retention
  • Escalation trigger to DAB if settlement failed
Section 03

The result

Negotiated settlement reached at approximately USD 2.1M LD payment — a 75% reduction from the initial LD notice. Retention released as part of the settlement package.

The contractor accepted the settlement to preserve the client relationship (one of a repeat-client group) and avoid escalation to DAB. The defence position would have supported further reduction at DAB, but the commercial trade-off favoured settlement.

The contractor engaged Ashforte on a Portfolio Retainer specifically to prevent recurrence — with focus on notice discipline and live claim positioning across every project, so future defence work would start with a stronger record base.

Section 04

Lessons

The lessons from an engagement are usually more transferable than the specific results. What Ashforte's clients typically take away from case studies like this one:

01

Defensive positioning against LDs benefits enormously from a live claim position maintained through the project. Building defence from a cold record base is possible but constrained by what the records will support.

02

75% reduction on the LD notice was a strong outcome given the record base — but the record base was the ceiling on how far the position could go.

03

The client-relationship value of a negotiated settlement often outweighs the incremental recovery available through escalation. The contractor made the right commercial trade-off.

Service pillar

This engagement sat within Claims & Dispute Support.

Entitlement identified early. Claims built on evidence. Defence positions ready before they're needed.

Explore Claims & Disputes
By Invitation — No Cost

Initial Commercial Risk Assessment

By invitation, Ashforte provides qualified contractors with an initial commercial risk assessment on one live project. A structured senior review of contract, claims and commercial-control exposure, delivered as a documented briefing with a 30-day action plan. Qualification is determined in the first conversation.

A structured review of one live project — offered by invitation, at no cost, to qualified contractors.

Request an initial assessment
What's included
  • 01Review of selected project documents (contract, correspondence, variations, programme)
  • 02Identification of key contract and commercial risk exposures
  • 03Short maturity assessment across notices, variations, claims and payment controls
  • 04A practical 30-day action plan
  • 05Findings call with the project or commercial lead
Typically appropriate for
  • Contractors with active commercial pressure on a live project
  • Variation or claims exposure requiring senior review
  • Payment or certification issues affecting cash
  • Stretched commercial teams needing external senior view
  • Final account or close-out situations